If approved by council, when will all this be happening?

We are still in the very early stages of our development application, so we are many months away from starting construction.

If the development were to be approved by North Sydney Council, our construction timeline would include an approximate timeline of 18 months to have the project completed.

This includes, demolition, structure, fit out, public domain and landscape works. This timeframe is susceptible to the influence of construction hours and timings.

Please refer to our website for the latest timeline as this will be updated regularly to reflect the status of the development approval and construction progress.